The project and your building’s connection
On 14 September, Cannes reported progress towards a planned spring 2027 launch. The scheme provides for 8.7 km of network serving 95 buildings in La Frayère, Ranguin and Bastide Rouge, 35 GWh of annual heat and an 80% renewable-energy share.
For a particular building, obtain confirmation of its connection, the supply date and the proposed contract. These documents connect the network’s overall plans with the apartment’s future costs.
Documents to request from the building manager
| Document | Check |
|---|---|
| General-meeting resolutions | Connection approval and expenditure accepted by owners |
| Contract and schedules | Duration, tariff, indexation, capacity and responsibilities |
| Building works programme | Substation, internal equipment, timing and transition arrangements |
| Co-ownership budget | Funding, maintenance, allocation and advance payments |
Establish whether the arrangement covers hot water, space heating or both. Compare proposed charges with the existing contract and any outstanding boiler commitments. Identify disconnection, adaptation and maintenance costs separately.
Treat savings as a forecast
The agglomeration forecasts a heating-bill reduction of about 15%. This is the project promoter’s estimate. For your apartment, compare two annual budgets at the same consumption level: the current contract and the proposed district-heating tariff. Include fixed charges, maintenance and transition costs.
Compare complete annual costs for similar use. A reduction in the energy price is not necessarily the same reduction in total co-ownership charges, which also fund other services.
Before the preliminary agreement
Give the documents to the notary and clarify which approved decisions and payments relate to the lot and how the sale records them. Without an approved schedule, do not make forecast savings essential to affordability.
The network may change heating provision and the cost structure. It does not prove a property-value uplift. For another neighbourhood development, see the La Bocca market opening.
Sources and verification date
Checked on 21 September 2026. Observation periods and limitations are identified in the article.